Table of Contents

previous Home next

2.05.01 Earned-Value-Analysis

The chart Earned-Value-Analysis lists the planned and actual time/effort (in hours or person-days) for a project over any time period, as well as the degree of completion (progress for the previous period). From this data Earned Value and further key figures (BCWS, ACWP und BCWP) is determined. With Earned-Value-Analysis, not only the planned and actual values, but also a third value (BCWP, also stated in hours) can be used for the project evaluation.

Tip: For more on this subject see chapter 4.12 Applying Charts and 3.12.01 Earned Value Analysis

The form consists of the following elements:

1. Name

2. Input Data

3. Main Parameters

4. Further Criteria

5. Adjustment of Chart Display

6. Results

The results of the already processed chart are found in this tab.