Cost Center: In this selection box you can choose cost centers as selection criteria. These cost centers refer to the employees' cost center and restrict the selection of the employees considered accordingly (only employees assigned to this (these) cost center(s) are displayed).
Project Type: In this selection box, you can choose project type as a selection criterion. These types refer to the category of the project and restrict the selection of the project accordingly (only projects assigned to this (these) project type(s) are displayed).
External Order: This selection refers to the external indicator of the project and restricts the selection of the project accordingly (only external projects are displayed).
Operation: This selection refers to the operation indicator of the project and restricts the selection of the project accordingly (only projects for which the checkbox is set are displayed).
Period: This selection box is used in the capacity evaluation to define a period (weekly, monthly, …) for the consideration of the capacities for the selected employees.
Highpoint on the Scale: Here you can specify the highest point of the scale.
Display of Capacity in: This selection controls the display form of the capacity. Possible displays are in %, h or Pt.
Project Status: This selection filters the corresponding status of the project. Only projects of selected statuses are displayed.
Upper Utilization Limit: This selection controls the upper utilization limit, above which a colored highlighting in red takes place.
Lower Utilization Limit: This selection controls the lower utilization limit. All workloads that are smaller than the entered value are displayed in green in graphical views.
Workload Grouped on Projects: This checkbox controls the display of the evaluation in relation to projects, work packages and activities. If the checkbox is set, the workloads are displayed per project and no longer per work package or activity.
Surpress AP Details: This selection controls the display of the evaluation at activity or work package level. If the checkbox is set, the activities are displayed.
Display Abscences: If you check this box, abscences will be displayed.