The planned costs specify the internal cost which are based on the planning data of the [[en:handbuch:kapitel_2:2.02.04_arbeitspaket|jobs]] and from the [[en:handbuch:kapitel_2:2.02.09_budget|budget administration]]. The internal costs are determined from tracking and recording ([[en:handbuch:kapitel_2:2.3.01_timetracker|TimeTracker]]) and [[en:handbuch:kapitel_2:2.03_erfassungsmodul|cost recording]]. The project budget is, if necessary, defined in the project and the planned revenue is calculated from the external evaluation of the jobs and budget administration. The external revenue specifies all billable services in the system (time and costs). | The planned costs specify the internal cost which are based on the planning data of the [[en:handbuch:kapitel_2:2.02.04_arbeitspaket|jobs]] and from the [[en:handbuch:kapitel_2:2.02.09_budget|budget administration]]. The internal costs are determined from tracking and recording ([[en:handbuch:kapitel_2:2.3.01_timetracker|TimeTracker]]) and [[en:handbuch:kapitel_2:2.03_erfassungsmodul|cost recording]]. The project budget is, if necessary, defined in the project and the planned revenue is calculated from the external evaluation of the jobs and budget administration. The external revenue specifies all billable services in the system (time and costs). | ||
- | + | {{:en:handbuch:kapitel_3:project_overview.jpg|}} | |
- | {{:handbuch:kapitel_4:praxis:4-reports-pr1.gif?direct}} | + | |
===== Project Structure Plan (Work Breakdown Structure) ===== | ===== Project Structure Plan (Work Breakdown Structure) ===== | ||
- | The Work Breakdown Structure diagram illustrates the project structure. The [[en:handbuch:kapitel_a:glossar# Work Breakdown Structure]] (project structure plan) in Projectile displays the relationship of the [[en:handbuch:kapitel_a:glossar#project]] and the sub-projects with the corresponding [[en:handbuch:kapitel_a:glossar#jobs]]. The logical structure of the project (project structure/project hierarchy) down to the jobs level is visualized graphically. This chart also contains important planned and actual data of the projects, sub-projects and jobs. | + | The Work Breakdown Structure diagram illustrates the project structure. The [[en:handbuch:kapitel_a:glossar# work breakdown structure]] (project structure plan) in Projectile displays the relationship of the [[en:handbuch:kapitel_a:glossar#project]] and the sub-projects with the corresponding [[en:handbuch:kapitel_a:glossar#jobs]]. The logical structure of the project (project structure/project hierarchy) down to the jobs level is visualized graphically. This chart also contains important planned and actual data of the projects, sub-projects and jobs. |
- | {{:handbuch:kapitel_4:praxis:4-reports-pr2.gif?direct}} | + | {{:en:handbuch:kapitel_3:psp_chart1.jpg|}} |
===== Project Chart Target/Actual ===== | ===== Project Chart Target/Actual ===== | ||
Line 39: | Line 38: | ||
The chart can display the planned data and actual data graphically, if the option "with image" (format tab) is set. | The chart can display the planned data and actual data graphically, if the option "with image" (format tab) is set. | ||
- | {{:handbuch:kapitel_4:praxis:4-reports-pr4.gif?direct}} | + | {{:en:handbuch:kapitel_3:project_target_actual1.jpg|}} |
+ | {{:en:handbuch:kapitel_3:project_target_actual1a.jpg|}} | ||
===== Jobs Target/Actual ===== | ===== Jobs Target/Actual ===== | ||
Line 47: | Line 47: | ||
The chart also contains information for planned-start and planned-end of the jobs, of the status (including the due date) of the jobs and the estimated [[en:handbuch:kapitel_2:2.02.08_fertigstellungsgrad|degree of completion]] through TimeTracker. | The chart also contains information for planned-start and planned-end of the jobs, of the status (including the due date) of the jobs and the estimated [[en:handbuch:kapitel_2:2.02.08_fertigstellungsgrad|degree of completion]] through TimeTracker. | ||
- | {{:handbuch:kapitel_4:praxis:4-reports-pr5.gif?direct}} | + | {{:en:handbuch:kapitel_3:job_target_actual1.jpg|}} |
The chart can display the planned data and actual data graphically, if the option "with image" (format tab) is set. | The chart can display the planned data and actual data graphically, if the option "with image" (format tab) is set. | ||
Line 53: | Line 53: | ||
===== Milestone-Trend-Analysis ===== | ===== Milestone-Trend-Analysis ===== | ||
- | The Milestone-Trend-Analysis (MTA) chart displays trends for completing the defined [[en:handbuch:kapitel_a:glossar#Milestone|milestones]]. The milestone-trend-analysis is a future-based instrument used for controlling deadlines of a [[en:handbuch:kapitel_a:glossar#Projekt|project]]: On regular reporting dates, the project [[en:handbuch:kapitel_a:glossar#Terminplanung|scheduling]] is estimated through a query of trend data for the probable time of achieving the objective. | + | The Milestone-Trend-Analysis (MTA) chart displays trends for completing the defined [[en:handbuch:kapitel_a:glossar#milestones]]. The milestone-trend-analysis is a future-related instrument used for controlling deadlines of a [[en:handbuch:kapitel_a:glossar#project]]: On regular reporting dates, the project [[en:handbuch:kapitel_a:glossar#scheduling]] is estimated through a query of trend data for the probable time of achieving the objective. |
+ | Through the course of the curve, a trend can be concluded through the deadlines of the project. The due dates for the milestones can be administered in the document type [[en:handbuch:kapitel_2:2.02.06_trendtermin |deadline]]. | ||
- | Die Auswertung Meilenstein-Trend-Analyse zeigt die Trends für die Erreichung der definierten [[handbuch:kapitel_a:glossar#Meilenstein|Meilensteine]] an. Die Meilenstein-Trend-Analyse ist ein zukunftsbezogenes Instrument für die Terminkontrolle eines [[handbuch:kapitel_a:glossar#Projekt|Projektes]]: An regelmäßigen Berichtszeitpunkten wird die [[handbuch:kapitel_a:glossar#Terminplanung|Terminplanung]] des Projektes durch die Abfrage von Trenddaten der voraussichtlichen Zielerreichung neu geschätzt. Aus dem Kurvenverlauf läßt sich ein Trend über die Termintreue des Projektes ableiten. Die Trendtermine für die Meilensteine können im Dokumenttyp [[handbuch:kapitel_2:2.02.06_trendtermin|Trendtermin]] verwaltet werden. | + | The course of the curve for this chart is interpreted as follows: |
- | Der Verlauf der Kurven dieser Analyse wird wie folgt interpretiert: | ||
- | * steigender Kurvenverlauf bedeutet eine Verzögerung => Das Meilensteinziel wird/ist verspätet erreicht, | + | * an ascending curve means: a delayment => The milestone objective will be/is achieved late, |
- | * Kurvenverlauf waagerecht bedeutet Termintreue => Das Meilensteinziel wird/ist rechtzeitig erreicht und | + | * a horizontal curve means: deadline is met => The milestone objective will be/is achieved on time and |
- | * fallender Kurvenverlauf bedeutet: Das Meilensteinziel wird/ist verfrüht erreicht. | + | * a descending curve means: the milestone objective will be/is achieved too early. |
- | {{:handbuch:kapitel_4:praxis:4-reports-pr6.gif?direct}} | + | {{:en:handbuch:kapitel_3:chart_mta1.jpg|}} |
- | ===== Fertigstellungsgrad ===== | + | ===== Degree of Completion ===== |
+ | The **degree of completion** chart displays a graphical overview of the previous estimates for the projects and jobs. These estimates can be performed in the projects and/or the sub-projects or in [[en:handbuch:kapitel_2:2.3.01_timetracker|TimeTracker]] for the individual jobs. Further information can be found in chapter [[handbuch:kapitel_4:4.2.07_schaetzungen|4.2.7 Estimates]]. | ||
- | Die Auswertung Fertigstellungsgrad zeigt eine graphische Übersicht über die bisherigen Schätzungen für die Projekte und Arbeitspakete an. Diese Schätzungen können in den Projekten bzw. Unterprojekten oder im [[handbuch:kapitel_2:2.3.01_timetracker|TimeTracker]] für die einzelnen Arbeitspakete vorgenommen werden. Weitere Informationen befinden sich im Abschnitt [[handbuch:kapitel_4:4.2.07_schaetzungen|4.2.7 Schätzungen]]. | + | {{:en:handbuch:kapitel_3:completion_chart1.jpg|}} |
- | + | ||
- | {{:handbuch:kapitel_4:praxis:4-reports-pr7.gif?direct}} | + | |
===== Skill-Matrix ===== | ===== Skill-Matrix ===== | ||
+ | The **skill-matrix** chart provides an overview of the project services for the selected projects and sub-projects regarding the individual occupations. | ||