This shows you the differences between two versions of the page.
Both sides previous revision Previous revision Next revision | Previous revision | ||
en:gui5:handbuch:kapitel_2:2.02.12_statusbericht [2021/06/04 15:34] alexandra |
en:gui5:handbuch:kapitel_2:2.02.12_statusbericht [2021/12/09 10:47] (current) alexandra [Comments] |
||
---|---|---|---|
Line 14: | Line 14: | ||
* **Project:** This field displays the project selected at the beginning of the status report you created. | * **Project:** This field displays the project selected at the beginning of the status report you created. | ||
* **Reporting Period:** Enter the report period in this field. | * **Reporting Period:** Enter the report period in this field. | ||
- | * **Creator:** This field displays the employee who created the status report. | + | * **Created by:** This field displays the employee who created the status report. |
* **Report Date:** This field displays when this report was created. | * **Report Date:** This field displays when this report was created. | ||
* **Next Report Date:** In this field, the date for the next report can be entered. | * **Next Report Date:** In this field, the date for the next report can be entered. | ||
- | * **Expected Project End:** In this selection box, a date can be entered when the project should be completed. | + | * **Estimated Project End:** In this selection box, a date can be entered when the project should be completed. |
- | * **Comment:** This field allows you to enter a comment about the opened status report. | + | * **Note:** This field allows you to enter a comment about the opened status report. |
- | * **Current Status Report:** This flag is used for cross-project status reports (so that the most current one can be displayed). | + | * **Current Report:** This flag is used for cross-project status reports (so that the most current one can be displayed). |
* **Status:** | * **Status:** | ||
- | * **Status of Dates, Costs and Quality:** The status of dates, costs and quality can be defined in these selection fields. You can choose between Favourable, Planned, Problematic and Critical. | + | * **Status of Deadlines, Costs, Quality and RessourceState:** The status of dates, costs and quality can be defined in these selection fields. You can choose between Favourable, Planned, Problematic and Critical. |
- | * **Remaining Internal Activity, Remaining External Activity:** In these fields, you can store estimated residual values in EUR for internal and external activity. | + | * **Remaining Internal Effort, Remaining External Effort:** In these fields, you can store estimated residual values in EUR for internal and external activity. |
Line 30: | Line 30: | ||
{{:en:gui5:handbuch:kapitel_2:bildschirmfoto_2021-06-04_um_15.20.10.png?|}} | {{:en:gui5:handbuch:kapitel_2:bildschirmfoto_2021-06-04_um_15.20.10.png?|}} | ||
- | * **Positive/Negative:** These fields allow you to enter positive or negative comments on the created status report. | + | |
- | * **Risks:** In these text fields, the project manager can enter critical factors or risks that could occur or have already occurred in the project. | + | * **Results Last Period:** In this field, you can list the results of the last period. |
- | * **Project Change Requests:** Here you can enter change requests for the project in text form. | + | * **Tasks Next Period:** Here you can enter the tasks for the next period. |
+ | * **Current Top Risks:** In these text field, the project manager can enter critical factors or risks that could occur or have already occurred in the project. | ||
+ | * **Current Decisions:** The current decisions can be listed here. | ||
+ | * **Change Requests:** Here you can enter change requests for the project in text form. | ||
===== Risk Assessment ===== | ===== Risk Assessment ===== |